Construction along Route 7

News & Updates

Project Updates Archives

Previous Construction Updates

July 2023

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Completed noise barrier foundation drilling and started post and panel installation along eastbound Route 7 between Bishopsgate Way and Markell Court.
  • Continued drilling noise barrier foundations and started post and panel installation along eastbound Route 7 between Utterback Store Road and Bishopsgate Way, 
  • Finished final surface paving for the left and center lanes on westbound Route 7 between Colvin Run Road (west) and Amanda Drive, and on eastbound Route 7 between Bishopsgate Way and Delta Glen Court.
  • Finished final surface paving for the right lane on eastbound Route 7 between Bishopsgate Way and Baron Cameron Avenue.

Area 2: Baron Cameron Avenue Intersection

  • Completed curb installation at the Baron Cameron Avenue intersection.

Area 3: Difficult Run Area (Colvin Forest Drive to Faulkner Drive

  • Poured the concrete barrier between the westbound Route 7 travel lanes and the shared use path on the Difficult Run bridge, completing all bridge construction over Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Completed final surface paving for the left and center lanes on eastbound Route 7 between Trap Road and Jarrett Valley Drive.
  • Continued storm sewer installation at Wolftrap Run Road.
  • Placed intermediate asphalt for Stage 3B between Difficult Run and Lyons Street, and between Towlston Road and Lucky Estates Drive. 

Project-Wide

  • Third-party utility relocation activities are ongoing.
  • Continued fence installation at stormwater management ponds.
  • Continued grading, placement of stone and paving for the shared-use paths.

Click here to see July 2023 photos.

June 2023

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Continued drilling noise barrier foundations along eastbound Route 7 between Bishopsgate Way and Markell Court.
  • Started final surface paving and pavement markings on westbound Route 7 between Colvin Forest Drive and Amanda Drive.

Area 2: Baron Cameron Avenue Intersection

  • Completed milling and temporary asphalt removal for Stage 3B.
  • Shifted traffic on westbound Route 7 at the Baron Cameron Avenue intersection to the south.

Area 3: Difficult Run Area (Colvin Forest Drive to Faulkner Drive

  • Completed asphalt milling for Stage 3B and placed curb stone between the pedestrian underpass and Faulkner Drive.
  • Completed construction of the concrete barrier between the eastbound Route 7 travel lanes and the shared use path on the Difficult Run bridge.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Completed noise barrier panel installation along westbound Route 7 between Towlston Road and 400 feet west of Lyons Street.
  • Placed curb, stone, and base asphalt between Faulkner Drive and Beulah Road.
  • Placed stone, installed drop inlet tops for new stormwater management infrastructure, poured curb, and put down base asphalt for Stage 3B between Beulah Road and Lewinsville Road.  
  • Placed and backfilled curb between Lewinsville Road and Jarrett Valley Drive.

Project-Wide

  • Third-party utility relocation activities are ongoing.
  • Completed installation of Intelligent Transportation Systems (ITS) fiber optic cable for traffic signal communication throughout the project. 
  • Continued grading, placement of stone and paving for the shared-use path.

Click here to see June 2023 photos.

May 2023

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Completed surface paving along eastbound and westbound Route 7 between Reston Avenue and Utterback Store Road.
  • Began installation of final pavement markings between Reston Avenue and Utterback Store Road.
  • Commenced surface paving along eastbound and westbound Route 7 between Utterback Store Road and Amanda Drive.

Area 2: Baron Cameron Avenue Intersection

  • Started milling existing asphalt in preparation for completing the shift to Stage 3B.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Completed deck grooving on westbound bridge.
  • Backfilled curb and placed intermediate asphalt for Stage 3A between Serenity Woods Lane and Carpers Farm Way. 
  • Opened new Difficult Run bridge on westbound Route 7 to traffic.
  • Began milling existing asphalt for Stage 3B between Faulkner Drive and the pedestrian underpass.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Completed noise barrier post installation along westbound Route 7 between Towlston Road and Lyons Street.
  • Completed noise barrier panel installation along westbound Route 7 on the east side of Trotting Horse Lane.
  • Milled existing asphalt, placed cement-treated aggregate, and base asphalt for Stage 3B between Atwood Road and Lucky Estates Drive.
  • Continued storm sewer installation between Towlston Road and Lucky Estates Drive.
  • Placed asphalt for Stage 3B between Jarrett Valley Drive and Lewinsville Road.

Click here to see May 2023 photos.

April 2023

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Began drilling noise barrier foundations along eastbound Route 7 between Bishopsgate Way and Markell Court.
  • Set noise barrier panels along eastbound Route 7 east of Reston Parkway.

Area 2: Baron Cameron Intersection

  • Continued construction of the improvements at the Route 7/Baron Cameron Avenue intersection.
  • Began construction of the extension of the third westbound lane on Baron Cameron Avenue through the Hunter Gate Way intersection.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Constructed the bridge rail and approach slabs for the new Difficult Run bridge on westbound Route 7.
  • Placed cement-treated aggregate, base asphalt, and installed curb returns along westbound Route 7 between Faulkner Drive and Carpers Farm Way.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Completed noise barrier foundation drilling along westbound Route 7 between Towlston Road and Lyons Street.
  • Completed noise barrier and retaining wall post installation along westbound Route 7 between Forestville Drive and Trotting Horse Lane.
  • Continued paving between Faulkner Drive and Beulah Road.
  • Completed rough grading at the stormwater management pond west of Trotting Horse Lane.
  • Placed cement-treated aggregate and base asphalt and installed curb along eastbound Route 7 between Towlston Road and Lucky Estates Drive.
  • Shifted eastbound Route 7 traffic and began milling existing asphalt between Atwood Drive and Lucky Estates Drive.
  • Continued paving operations between Lucky Estates Drive and Lewinsville Road.

Click here to see April 2023 photos.

March 2023

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Continued construction of the shared-use paths along Route 7.
  • Drilled noise barrier foundations along westbound Route 7 near Springvale Road.

Area 2: Baron Cameron Intersection

  • Continued construction of the improvements on Baron Cameron Avenue between Route 7 and Hunter Gate Way.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Completed storm sewer installation for Stage 3A between the east end of Colvin Run Road and Faulkner Drive.
  • Placed concrete for the deck of the new Difficult Run bridge on westbound Route 7.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Installed noise barrier panels along eastbound Route 7 between Towlston Road and Jill's House.
  • Completed drilling for the foundations of the retaining wall along westbound Route 7 near Faulkner Drive.
  • Completed storm sewer installation for Stage 3A between Towlston Road and Lucky Estates Drive.
  • Continued earth-moving activities, grading, and placement of soil cement along eastbound Route 7 between Towlston Road and Lucky Estates Drive.
  • Began base asphalt paving and curb construction along eastbound Route 7 between Beulah Road and Atwood Road, and between Lucky Estates Drive and Lewinsville Road.
  • Completed rough excavation for the stormwater management pond between Wolftrap Run Road and Jill's House.

Click here to see March 2023 photos.

February 2023

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Continued construction of the shared-use paths along Route 7.

Area 2: Baron Cameron Intersection

  • Constructed the curb for the eastbound Route 7 turn lane to Baron Cameron Avenue.
  • Continued construction of the improvements on Baron Cameron Avenue between Route 7 and Hunter Gate Way.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Completed construction of the backwalls of the bridge abutments.
  • Began forming the bridge deck and installing the deck rebar for the new Difficult Run bridge on westbound Route 7.
  • Continued storm sewer installation between the east end of Colvin Run Road and Difficult Run, and between Difficult Run and Faulkner Drive.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Continued noise barrier foundation drilling along eastbound Route 7 between Trap Road and Jill's House. 
  • Continued noise barrier post installation between Andrew Chapel Cemetery and Jill's House.
  • Continued construction of the retaining walls and noise barrier along westbound Route 7 between Forestville Drive and Trotting Horse Lane.
  • Completed construction of the retaining wall along eastbound Route 7 near Serenity Woods Lane.
  • Continued excavation for the stormwater management pond on the west side of McLean Bible Church.
  • Grading, placement of cement-treated aggregate, and base asphalt paving was completed along eastbound Route 7 between Serenity Woods Lane and Atwood Road.

Click here to see February 2023 photos.

January 2023

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Continued construction of the shared-use paths along Route 7.

Area 2: Baron Cameron Intersection

  • Continued construction of the permanent right-turn lane from eastbound Route 7 to Baron Cameron Avenue and additional improvements at the southwest corner of the Route 7/Baron Cameron Avenue intersection.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Set girders and continued construction of the bridge abutments for the new Difficult Run bridge on westbound Route 7.
  • Continued storm sewer installation between the east end of Colvin Run Road and Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Continued noise barrier foundation drilling along eastbound Route 7 between Towlston Road and Lucky Estates Drive.
  • Continued noise barrier post installation near Atwood Road.
  • Removed existing asphalt along Route 7 between Beulah Road and Atwood Road, and between Lucky Estates Drive and Lewinsville Road.
  • Began excavation for the stormwater management pond on the west side of McLean Bible Church.
  • Earth-moving activities along eastbound Route 7 commenced between Beulah Road and Atwood Road.
  • Grading, placement of cement-treated aggregate, and base asphalt paving was completed along eastbound Route 7 between Atwood Road and Towlston Road.
  • Grading and placement of cement-treated aggregate began along eastbound Route 7 between Lucky Estates Drive and Lewinsville Road.

Click here to see January 2023 photos.

December 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Continued construction of the shared-use paths along Route 7.

Area 2: Baron Cameron Intersection

  • Continued construction of the permanent right-turn lane from eastbound Route 7 to Baron Cameron Avenue.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued construction of the foundations, substructure, and retaining wall for the new Difficult Run bridge on westbound Route 7.
  • Continued storm sewer installation between the new pedestrian underpass at Colvin Run Mill Park and Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Commenced construction of the noise barrier along westbound Route 7 west of Forestville Drive.
  • Continued noise barrier panel installation along eastbound Route 7 on the east and west sides of Old Ash Grove.
  • Paved along eastbound Route 7 between Middleton Ridge Road and Atwood Road and shifted traffic to the south.
  • Paved along eastbound Route 7 between Lucky Estates Drive and the east side of McLean Bible Church and shifted traffic to the south.
  • Opened new access to Lucky Estates Drive from Route 7.

Click here to see December 2022 photos.

November 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Continued construction of the shared-use paths along Route 7.
  • Shifted traffic on westbound Route 7 to the north between Colvin Run Road and Baron Cameron Avenue.

Area 2: Baron Cameron Intersection

  • Placed cement-treated aggregate, installed underdrain, constructed curb and gutter, and paved along eastbound Route 7 at Baron Cameron Avenue.
  • Shifted the temporary right-turn lane from eastbound Route 7 to Baron Cameron Avenue to the north in preparation for the construction of the permanent right-turn lane.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued construction of the foundations for the new Difficult Run bridge on westbound Route 7.
  • Continued storm sewer installation between the new pedestrian underpass at Colvin Run Mill Park and Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Continued noise barrier panel installation along eastbound Route 7 on the east and west sides of Old Ash Grove.
  • Completed curb construction along eastbound Route 7 and paved along eastbound Route 7 between Middleton Ridge Road and Beulah Road.
  • Placed cement-treated aggregate, installed underdrain, constructed curb and gutter, and paved along eastbound Route 7 between Beulah Road and Atwood Road.
  • Continued storm sewer installation between Trap Road and Wolftrap Run Road.
  • Placed cement-treated aggregate, installed underdrain, constructed curb and gutter, and paved along eastbound Route 7 between Trap Road and the east side of McLean Bible Church.

Click here to see November 2022 photos.

October 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Opened the third through-lane on westbound Route 7 to traffic.
  • Completed noise barrier panel installation along eastbound Route 7 between Baron Cameron Avenue and Delta Glen Court.
  • Continued grading for the shared-use path along eastbound Route 7 between Reston Avenue and Reston Parkway.

Area 2: Baron Cameron Intersection

  • Continued storm sewer installation , earth-moving activities, grading, and cement stabilization for Stage 3A.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Completed demolition of the remaining existing Difficult Run bridge.
  • Continued construction of the foundations for the new Difficult Run bridge on westbound Route 7.
  • Continued storm sewer installation between the new pedestrian underpass at Colvin Run Mill Park and Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Continued noise barrier panel installation along westbound Route 7 on the east side of Forestville Drive. 
  • Continued storm sewer installation for Stage 3A between Newcombs Farm Road and Beulah Road.
  • Continued grading, placement of cement-treated aggregate, and base asphalt placement along eastbound Route 7 between Middleton Ridge Road and Beulah Road.
  • Started underdrain and curb installation between Middleton Ridge Road and Atwood Drive.
  • Completed earth-moving activities and cement stabilization for Stage 3A between Beulah Road and Atwood Drive.  
  • Began storm sewer installation for Stage 3A between Lucky Estates Drive and Wolftrap Run Road.  
  • Started underdrain and curb installation and continued asphalt placement between Trap Road and the west side of McLean Bible Church.  
  • Completed storm sewer installation for Stage 3A between Wolftrap Run Road and the west side of McLean Bible Church. 

Click here to see October 2022 photos.

September 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Continued noise barrier post installation and started setting panels along Route 7 westbound between Springvale Road and Great Passage Boulevard.
  • Installed noise barrier posts along Route 7 eastbound between Baron Cameron Avenue and Delta Glen Court.
  • Started setting noise barrier panels along Route 7 eastbound between Reston Parkway and Bishopsgate Way.
  • Placed asphalt along westbound Route 7 between Colvin Forest Drive and Baron Cameron Avenue.
  • Continued construction of the shared use path along Route 7 westbound between Colvin Forest Drive and Downey Drive.

Area 2: Baron Cameron Intersection

  • Shifted traffic on Route 7 eastbound to the north and continued reconstruction of the Baron Cameron Avenue intersection, including earth-moving activities and storm sewer installation.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued demolition of the remaining existing Difficult Run bridge.
  • Began construction of the foundations for the new Difficult Run bridge on westbound Route 7.
  • Continued storm sewer installation between the new pedestrian underpass at Colvin Run Mill Park and Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Began noise barrier post installation Route 7 westbound on the east side of Forestville Drive. 
  • Installed noise barrier posts along Route 7 eastbound near Stokley Way and between Laurel Hill Road and Jarrett Valley Drive.
  • Completed noise barrier panel installation along Route 7 eastbound on the west side of Middleton Ridge Road.
  • Continued storm sewer installation between Newcombs Farm Road and Beulah Road.
  • Continued grading, placement of cement-treated aggregate, and base asphalt placement along eastbound Route 7 between Middleton Ridge Road and Beulah Road.
  • Continued storm sewer installation between Wolftrap Run Road and Lewinsville Road.
  • Continued earth-moving activities at the stormwater management pond between Wolftrap Run Road and McLean Bible Church.

Click here to see September 2022 photos.

August 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

  • Placed cement-treated aggregate, installed underdrain, constructed curb and gutter, and paved along westbound Route 7 between Colvin Forest Drive and Baron Cameron Avenue in preparation for upcoming traffic shift to Stage 3B.
  • Finished stone and asphalt placement for the shared use paths along eastbound and westbound Route 7 between Delta Glen Court/Colvin Run Road (west) and Colvin Forest Drive.

Area 2: Baron Cameron Intersection

  • Completed intermediate asphalt placement for Stage 2C and continued intersection reconstruction work.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Completed Stage 3A traffic shifts for eastbound and westbound Route 7 onto the new Difficult Run Bridge. 
  • Started removal of the remaining existing Difficult Run bridge. 
  • Began storm sewer installation between the new pedestrian underpass at Colvin Run Mill Park and Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Started drilling for noise barrier foundations along westbound Route 7 on the east and west sides of Forestville Drive. 
  • Began noise barrier post installation along eastbound Route 7 between Old Ash Grove and Jarrett Valley Drive. 
  • Installed retaining and noise barrier panels along eastbound Route 7 between Serenity Woods Lane and Middleton Ridge Road.  
  • Continued storm sewer installation between Newcombs Farm Road and Beulah Road.
  • Started grading, placement of cement-treated aggregate, and base asphalt placement along eastbound Route 7 between Middleton Ridge Road and Beulah Road.
  • Continued storm sewer installation between Wolftrap Run Road and Lewinsville Road.
  • Opened the new Lewinsville Road intersection, including the displaced left turn from eastbound Route 7 to Lewinsville Road, in an interim configuration. Improvements in this area are ongoing while crews complete the work for the opening of the permanent intersection configuration.

Click here to see August 2022 photos.

July 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue

  • Completed drilling for noise barrier foundations along westbound Route 7 between Riva Ridge Drive and Great Passage Boulevard.
  • Completed noise barrier post installation along westbound Route 7 between Amanda Drive and Riva Ridge Drive, and started post installation between Riva Ridge Drive and Baron Cameron Avenue.
  • Completed noise barrier panel installation along eastbound Route 7 between Reston Avenue and Reston Parkway.
  • Placed curb stone and base asphalt for Stage 3B between Amanda Drive and Baron Cameron Avenue.

Area 1 East: Baron Cameron Avenue to Carpers Farm Way

  • Began noise barrier post installation along eastbound Route 7 between Baron Cameron Avenue and Delta Glen Court.
  • Continued fine grading for Stage 3A along westbound Route 7 between Colvin Forest Drive and Baron Cameron Avenue.

Area 2: Baron Cameron Intersection

  • Placed cement-treated aggregate and asphalt for Stage 2C and continued intersection reconstruction work.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Completed stone and asphalt placement for Stage 2 between the pedestrian underpass at Colvin Run Mill Park and Serenity Woods Lane.
  • Finished construction of the approach slabs and outer bridge rail, completed deck grooving, and shifted eastbound Route 7 traffic to the new Difficult Run bridge.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Completed drilling for noise barrier foundations along eastbound Route 7 between Atwood Road and Towlston Road, and between Laurel Hill Road and Jarrett Valley Drive.
  • Continued storm sewer installation between Newcombs Farm Road and Beulah Road, and between Wolftrap Run Road and Lewinsville Road.
  • Placed curb stone, installed curb, and placed asphalt for Stage 3A between Serenity Woods Lane and Middleton Ridge Road. 
  • Completed storm sewer installation along the future right turn-lane from westbound Route 7 to the relocated portion of Lewinsville Road. 
  • Continued road construction activities at Lewinsville Road in preparation for the upcoming opening of the displaced left-turn lane.  

Click here to see July 2022 photos.

June 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue
  • Completed drilling for noise barrier foundations along eastbound Route 7 between Bishopsgate Way and Markell Court.
  • Placed cement-treated aggregate and base asphalt for Stage 3B between Amanda Drive and Baron Cameron Avenue.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Completed grading, placed cement-treated aggregate and asphalt, installed underdrain, and continued curb construction for Stage 3A along westbound Route 7 between Colvin Forest Drive and Baron Cameron Avenue.  
  • Continued noise barrier panel installation along westbound Route 7 between the two Colvin Run Road intersections and along eastbound Route 7 near Capital Church.
Area 2: Baron Cameron Intersection
  • Placed cement-treated aggregate and asphalt for Stage 2B.
  • Switched traffic on westbound Route 7 at Baron Cameron Avenue to Stage 2C.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Completed deck concrete placement for the eastbound bridge over Difficult Run.  
  • Began constructing the approach slabs and bridge rail on the eastbound bridge. 
  • Completed grading and placed cement-treated aggregate for Stage 2A on eastbound Route 7 between the pedestrian underpass and Serenity Woods Lane.
Area 4: Faulkner Drive to Jarrett Valley Drive
  • Completed storm sewer installation for Stage 3A between Middleton Ridge Road and Newcombs Farm Road.  
  • Performed grading and placed cement-treated aggregate and base asphalt along eastbound Route 7 for Stage 3A between Serenity Woods Lane and Middleton Ridge Road.  
  • Installed storm sewer along the future right turn-lane from westbound Route 7 to the relocated portion of Lewinsville Road. 
  • Continued road construction activities at Lewinsville Road in preparation for the upcoming opening of the displaced left-turn lane.
  • Completed reconstruction of the westbound right-turn lane from Route 7 to existing Lewinsville Road.

Click here to see June 2022 photos.

May 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue
  • Starting drilling for noise barrier foundations along eastbound Route 7 between Reston Parkway and Bishopsgate Way.
  • Continued paving and median curb construction between Utterback Store Road and Baron Cameron Avenue.  
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Completed post and panel installation for noise barriers along westbound Route 7 between Colvin Run Road (west) and Downey Drive, continued noise barrier panel installation between the two Colvin Run Road intersections.
  • Installed the arch sections and wingwalls for the north half of the pedestrian underpass at Colvin Run Mill Park.
  • Completed storm sewer installation and began pavement construction for Stage 3A between Baron Cameron Avenue and Colvin Forest Drive.
Area 2: Baron Cameron Intersection
  • Continued storm sewer installation, grading, stone placement, and paving at the Baron Cameron Avenue intersection.  
  • Reconstructed the right-turn lane from westbound Route 7 to Springvale Road.
  • Shifted the left-turn and through lanes of westbound Route 7 to the north.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Completed girder installation and began constructing the deck of the eastbound Route 7 bridge over Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Continued noise barrier construction along eastbound Route 7 near between Serenity Woods Lane and Middleton Ridge Road. 
  • Continued storm sewer installation, earth-moving, and road construction activities in preparation for the upcoming opening of the displaced left-turn lane at Lewinsville Road.  

Click here to see May 2022 photos.

April 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue
  • Completed base and intermediate paving and construction of median curb between Reston Avenue and Utterback Store Road. 
  • Continued paving and median curb construction between Utterback Store Road and Baron Cameron Avenue.
  • Installation of storm sewer infrastructure continued.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Completed drilling for noise barrier foundations along eastbound Route 7 between Baron Cameron Avenue and Delta Glen Court.
  • Completed post and panel installation for noise barriers along eastbound Route 7 on the east and west sides of Capital Church.
  • Completed footing installation for the north half of the pedestrian underpass at Colvin Run Mill Park.  
  • Continued storm sewer installation and pavement construction for Stage 3A between Baron Cameron Avenue and Colvin Forest Drive.
Area 2: Baron Cameron Intersection
  • Grading and stone placement for temporary asphalt continued.
  • Starting paving at the Baron Cameron Avenue intersection and reconstructing the right-turn lane from westbound Route 7 to Springvale Road in preparation for upcoming traffic shift. 

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued construction of the eastbound Route 7 bridge over Difficult Run, including girder installation.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Continued storm sewer installation, earth-moving, and road construction activities in preparation for the upcoming opening of the displaced left-turn lane at Lewinsville Road.  
  • Completed post installation for the noise barrier along westbound Route 7 adjacent to Towlston Road and started panel installation.
  • Completed post and panel installation for the retaining wall along southbound Towlston Road on the north side of Route 7 and began backfilling the area behind the retaining wall.  
  • Completed the 48" storm pipe crossing beneath Route 7 on the east side of McLean Bible Church and continued new storm sewer installation.

Click here to see April 2022 photos.

March 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue
  • Continued construction of the concrete curb along the Route 7 median between Reston Avenue and Baron Cameron Avenue.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Completed drilling for noise barrier foundations along westbound Route 7 between Springvale Road and Colvin Run Road (west).
  • Began drilling for noise barrier foundations along eastbound Route 7 between Baron Cameron Avenue and Delta Glen Court.
  • Completed excavation for the northern half of the pedestrian underpass at Colvin Run Mill Park.  
  • Continued storm sewer installation for Stage 3A between Baron Cameron Avenue and Colvin Forest Drive.
  • Continued installation of pavement for Stage 3A between Baron Cameron Avenue and Colvin Forest Drive.
Area 2: Baron Cameron Intersection
  • Storm sewer installation continued.
  • Grading and stone placement for temporary asphalt began.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued construction of the eastbound Route 7 bridge over Difficult Run.
  • Storm sewer installation for Stage 2A commenced between Carpers Farm Drive and Difficult Run. 
  • Completed noise barrier panel installation along eastbound Route 7 between Difficult Run and Serenity Woods Lane.  

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Began storm sewer installation and continued earth-moving activities for the upcoming displaced left-turn lane at Lewinsville Road.  
  • Continued drilling for noise barrier foundations and post and panel installation along eastbound Route 7 near Middleton Ridge Road, and along westbound Route 7 near Towlston Road.
  • Continued work on the 48" storm pipe crossing beneath Route 7 on the east side of McLean Bible Church.
  • Completed rough grading for the stormwater management pond east of McLean Bible Church.

Click here to see March 2022 photos.

February 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue
  • Started construction of the concrete curb along the Route 7 median between Reston Avenue and Baron Cameron Avenue.
  • Storm sewer installation west of Baron Cameron Avenue continued.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Continued panel installation for the noise barrier along westbound Route 7 between Colvin Run Road (east) and Colvin Run Road (west).
  • Started excavation for the northern half of the pedestrian underpass at Colvin Run Mill Park.  
  • Continued storm sewer installation for Stage 3A between Baron Cameron Avenue and Colvin Forest Drive.
Area 2: Baron Cameron Intersection
  • Continued storm sewer installation for Stage 2A west of Baron Cameron Avenue.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued construction of foundations for the piers and western abutment of the eastbound Route 7 bridge over Difficult Run, including the completion of the drilled shaft installation for Pier 1 and the excavation for Pier 2.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Continued grading and began placement of cement-treated aggregate and base asphalt for Stage 3B between Lewinsville Road and Jarrett Valley Drive.
  • Continued drilling for noise barrier foundations along eastbound Route 7 near Serenity Woods Lane.  
  • Started work on the 48" storm pipe crossing beneath Route 7 on the east side of McLean Bible Church.

Click here to see February 2022 photos.

January 2022

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 East: Baron Cameron Avenue to Carpers Farm Way:
  • Completed post installation and continued panel installation for the noise barrier along westbound Route 7 between Colvin Run Road (east) and Colvin Run Road (west).
  • Completed panel installation and began backfilling at the retaining wall along westbound Route 7 west of the pedestrian underpass at Colvin Run Mill Park.
  • Continued storm sewer installation for Stage 3A between Baron Cameron Avenue and Colvin Forest Drive.
Area 2: Baron Cameron Intersection
  • Completed storm sewer installation for Stage 2A east of Baron Cameron Avenue and continued storm sewer installation for Stage 2A west of Baron Cameron Avenue.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued construction of foundations for the piers and western abutment of the eastbound Route 7 bridge over Difficult Run, including drilled shaft installation for Pier 1 and excavation for Pier 2.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Continued earth-moving activities for Stage 3B between Lewinsville Road and Jarrett Valley Drive.
  • Starting drilling for noise barrier foundations along eastbound Route 7 near Serenity Woods Lane.  
  • Continued excavation of the stormwater management pond on the east side of McLean Bible Church. 
  • Completed storm sewer installation for the service road between McLean Bible Church and Laurel Hill Road. 
  • Shifted traffic to Stage 3A between Lyons Street and Lewinsville Road.

Click here to see January 2022 photos.

December 2021

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Completed drilling for noise barrier foundations west of Reston Parkway along eastbound Route 7. 
  • Storm sewer installation west of Baron Cameron Avenue continued.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way:
  • Continued post installation for the noise barrier wall along westbound Route 7 between Colvin Run Road (east) and Colvin Run Road (west).
  • Storm sewer installation between Baron Cameron Avenue and Colvin Forest Drive continued.
Area 2: Baron Cameron Intersection
  • Continued earth-moving activities at the intersection of Route 7 and Baron Cameron Avenue.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued construction of the retaining wall between eastbound Route 7 and the Colvin Run stream channel.
  • Construction of foundations for the piers and western abutment of the eastbound Route 7 bridge over Difficult Run continued.
  • Completed storm sewer installation for Stage 2 between Difficult Run and Serenity Woods Lane.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Completed storm sewer installation for Stage 3A between Serenity Woods Lane and Middleton Ridge Road.  
  • Installed underdrain, curb, and placed base and intermediate asphalt for Stage 2 between Towlston Road and Lewinsville Road. 
  • Placed base and intermediate asphalt between Lyons Street and Towlston Road.  
  • Completed the jack and bore storm sewer pipe crossing underneath Route 7 between Middleton Ridge Road and Newcombs Farm Road.  
  • Earth-moving activities for Stage 3B commenced between Lewinsville Road and Jarrett Valley Drive.
  • Began installing storm sewer for the service road between McLean Bible Church and Laurel Hill Road. 

Click here to see December 2021 photos.

November 2021

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Started drilling for noise barrier foundations west of Reston Parkway along eastbound Route 7. 
  • Paving for the shared-use path along westbound Route 7 was completed between Utterback Store Road and Reston Parkway, and paving of the shared-use path along eastbound Route 7 between Markell Court and Crippen Vale Court began. The shared-use paths will remain closed until later in the project due to ongoing construction activities in these areas. 
  • Storm sewer installation west of Baron Cameron Avenue continued.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way:
  • Continued noise barrier post and panel installation along eastbound Route 7 between Delta Glen Court and Colvin Forest Drive.
  • Started installing posts for the combination noise barrier/retaining wall along westbound Route 7 between Colvin Run Road (east) and Colvin Run Road (west).
  • Storm sewer installation between Baron Cameron Avenue and Colvin Forest Drive continued.
Area 2: Baron Cameron Intersection
  • Continued earth-moving activities at the intersection of Route 7 and Baron Cameron Avenue.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued construction of the retaining wall between eastbound Route 7 and the Colvin Run stream channel.
  • Construction of foundations for the piers and western abutment of the eastbound Route 7 bridge over Difficult Run continued.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Continued drilling for noise barrier foundations along westbound Route 7 west of Towlston Road, and for the retaining wall at the intersection of westbound Route 7 and Towlston Road.
  • Completed Stage 2A storm sewer installation, performed grading, and placed cement treated aggregate along westbound Route 7 between Towlston Road and Trap Road.
  • Performed grading, placed cement-treated aggregate and base asphalt, and completed curb construction along westbound Route 7 between Lyons Street and Towlston Road.
  • Continued paving and curb placement along westbound Route 7 between Towlston Road and Lewinsville Road.
  • Completed the jack and bore storm sewer pipe crossing underneath Route 7 between Lewinsville Road and Laurel Hill Road.

Click here to see November 2021 photos.

October 2021

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Completed grading for the shared use path along westbound Route 7 between Utterback Store Road and Reston Avenue.
  • Began grading for the shared use path along eastbound Route 7 between Markell Drive and Crippen Vale Court.·  
  • Completed demolition of temporary asphalt in the Route 7 median between Reston Avenue and Amanda Drive.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way:
  • Completed drilling for noise barrier foundations along westbound Route 7 between the east end of Colvin Run Road and Springvale Road.
  • Continued noise barrier post and panel installation along eastbound Route 7 near Colvin Forest Drive.
  • Storm sewer installation between Baron Cameron Avenue and Colvin Forest Drive continued.
  • Completed water main relocation work between Baron Cameron Avenue and Downey Drive.
Area 2: Baron Cameron Intersection
  • Continued earth-moving activities at the intersection of Route 7 and Baron Cameron Avenue.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued construction of the retaining wall between eastbound Route 7 and the Colvin Run stream channel.
  • Completed maintenance work on the Potomac Interceptor sanitary sewer. 
  • Construction of foundations for the piers and western abutment of the eastbound Route 7 bridge over Difficult Run continued.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Started drilling for noise barrier foundations along westbound Route 7 west of Towlston Road.
  • Continued storm sewer installation along westbound Route 7 between Lewinsville Road and Royal Estates Drive, and between Towlston Road and Lyons Street.
  • Continued storm sewer installation along eastbound Route 7 between Towlston Road and Trap Road.
  • Shifted traffic on westbound Route 7 to the north between Lyons Street and Trotting Horse Lane.
  • Completed pipe installation for the water main distribution relocations between Towlston Road and Lewinsville Road.
  • Performed grading and placed cement-treated aggregate along westbound Route 7 between Lewinsville Road and Royal Estates Drive. 
  • Continued storm sewer pipe crossings underneath Route 7 between Lewinsville Road and Laurel Hill Road.

Click here to see October 2021 photos.

September 2021

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Completed removal of old asphalt along westbound Route 7 between Baron Cameron Avenue and Amanda Drive.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way:
  • Started drilling for noise barrier posts along westbound Route 7 east of Colvin Run Road (west end).
  • Storm sewer installation between Baron Cameron Avenue and Colvin Forest Drive continued.
  • Began grading for eastbound Route 7 shared use path east of Baron Cameron Avenue.
Area 2: Baron Cameron Intersection
  • Continued earth-moving activities at the intersection of Route 7 and Baron Cameron Avenue.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Started drilling for noise barrier posts along eastbound Route 7 on the east side of Colvin Forest Drive.
  • Installed storm sewer for eastbound Route 7 west of Serenity Woods Lane.
  • Placed embankment for eastbound Route 7 east of Carpers Farm Way.
  • Continued construction of the retaining wall between eastbound Route 7 and the Colvin Run stream channel.
  • Continued maintenance on the Potomac Interceptor sanitary sewer.
  • Abutment construction continued for the eastbound Route 7 bridge on the east side of Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Completed grading and placement of cement-treated aggregate, asphalt and curb construction along westbound Route 7 between Lyons Street and Trotting Horse Lane.
  • Shifted traffic on westbound Route 7 to the north between Lyons Street and Forestville Drive.
  • Shifted traffic on eastbound Route 7 to the south between Lewinsville Road and Jarrett Valley Drive.
  • Continued pipe installation for the water main distribution relocations between Towlston Road and Lewinsville Road.
  • Started storm sewer pipe crossings underneath Route 7 between Lewinsville Road and Laurel Hill Road.

Click here to see September 2021 photos.

August 2021

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Constructed curb and placed asphalt along westbound Route 7 between Reston Parkway and Reston Avenue, and between Great Passage Boulevard and Utterback Store Road.
  • Completed new alignment of the Utterback Store Road/Route 7 intersection and opened it to traffic.
  • Shifted traffic on westbound Route 7 between Reston Parkway and Reston Avenue to the north.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way:
  • Continued drilling for noise barrier posts for Wall G3 along eastbound Route 7 east of Capital Church.
  • Continued storm drainage installation along eastbound Route 7.
Area 2: Baron Cameron Intersection
  • Continued earth-moving activities at the intersection of Route 7 and Baron Cameron Avenue.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued construction of the retaining wall between eastbound Route 7 and the Colvin Run stream channel.
  • Completed installation of steel piles and began construction of the abutment (structure that supports one end of a bridge) of the eastbound Route 7 bridge on the east side of Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Continued storm sewer installation along westbound Route 7 between Towlston Road and Lewinsville Road.
  • Constructed curb along westbound Route 7 between Towlston Road and Forestville Drive.
  • Began grading and placement of cement-treated aggregate, base asphalt and curb stone along westbound Route 7 between Royal Estates Drive and Towlston Road.
  • Continued storm sewer pipe crossings between Towlston Road and Lewinsville Road. 
  • Continued pipe installation for the water main distribution relocations between Towlston Road and Lewinsville Road.

Click here to see August 2021 photos.

July 2021

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Completed noise barrier panel installation along westbound Route 7 between Utterback Store Road and Great Passage Boulevard.
  • Performed grading, placed cement-treated aggregate and asphalt, and placed curb stone along westbound Route 7 between Reston Parkway and Reston Avenue, and between Great Passage Boulevard and Utterback Store Road.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way:
  • Completed drilling for noise barrier posts along eastbound Route 7 for Walls G4 and G5 west of Colvin Forest Drive.
  • Starting drilling for noise barrier posts for Wall G3 along eastbound Route 7 east of Capital Church.
Area 2: Baron Cameron Intersection
  • Continued earth-moving activities at the intersection of Route 7 and Baron Cameron Avenue.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Constructed the permanent pavement on Carpers Farm Way.
  • Continued construction of the retaining wall between eastbound Route 7 and the Colvin Run stream channel.
  • Continued installation of steel piles for the eastbound bridge over Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Continued storm sewer installation along westbound Route 7 between Trotting Horse Lane and Towlston Road, and commenced storm sewer installation between Towlston Road and Lewinsville Road.
  • Began grading and placement of cement-treated aggregate, curb stone, and asphalt along westbound Route 7 between Beulah Road/Springvale Road and Towlston Road.
  • Started storm sewer pipe crossings between Towlston Road and Lewinsville Road. 
  • Continued water main distribution relocations and tie-ins to existing infrastructure between Towlston Road and Lewinsville Road.

Click here to see July 2021 photos.

June 2021

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Noise barrier panel installation commenced along westbound Route 7 between Utterback Store Road and Great Passage Boulevard.
  • Completed drilling for noise barrier posts along eastbound Route 7 between Colvin Forest Drive and Serenity Woods Lane.
  • Crews installed storm sewer between Reston Avenue and Great Passage Boulevard.
  • Performed grading, placed cement-treated aggregate and asphalt, and installed curb along westbound Route 7 between Baron Cameron Avenue and Amanda Drive.
  • Continued earth-moving activities at the intersection of Route 7 and Baron Cameron Avenue.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Continued construction of the retaining wall between eastbound Route 7 and the Colvin Run stream channel.
  • Began excavation of the new Difficult Run bridge foundation and the abutment on the east side of the bridge.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Installed the outfall structure in the stormwater management pond near Towlston Road.
  • Continued water main distribution relocations between Towlston Road and Lewinsville Road.
  • Completed placement of cement-treated aggregate, curb stone, and asphalt between Lewinsville Road and Old Ash Grove for upcoming traffic shift.

Click here to see June 2021 photos.

May 2021

Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Noise barrier construction continued between Utterback Store Road and Great Passage Boulevard.
  • Crews installed storm sewer between Reston Avenue and Baron Cameron Avenue.
  • Backfilled curb and placed asphalt along westbound Route 7 between Reston Parkway and Utterback Store Road.
  • Performed grading between Utterback Store Road and Great Passage Boulevard.  
Area 1 East: Baron Cameron Avenue to Colvin Forest Drive:
  • Completed the tie-in of the Fairfax County Water Authority's 54" water main relocation between Colvin Forest Drive and Carpers Farm Way along eastbound Route 7. 
  • Continued earth-moving activities at the intersection of Route 7 and Baron Cameron Avenue.
  • Completed excavation for the retaining wall between eastbound Route 7 and the Colvin Run stream channel and commenced footing construction.  
  • Construction of the south half of the pedestrian underpass at Colvin Run Mill Park was ongoing. 
  • Backfilled curb and placed asphalt along westbound Route 7 between Middleton Ridge Road and Trotting Horse Lane.
  • Commenced water main distribution relocations near Towlston Road.
  • Installed, tested, and tied in the Fairfax County Water Authority's 54" water main relocation along eastbound Route 7 between Wolftrap Run Road and Lewinsville Road.
  • Placed cement-treated aggregate and base asphalt, and performed fine grading between Lewinsville Road and Old Ash Grove.
  • Began clearing for relocated Lewinsville Road.

Click here to see May 2021 photos.

April 2021

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Completed noise barrier panel installation between Reston Avenue and Utterback Store Road.
  • Installed permanent signal poles at Reston Parkway and Utterback Store Road.
  • Completed construction of the curb along westbound Route 7 between Reston Parkway and Utterback Store Road.
  • Storm sewer installation and earth-moving activities continued between Reston Avenue and Baron Cameron Avenue.
  • Placed cement-treated aggregate and base asphalt between Amanda Drive and Baron Cameron Avenue.
Area 1 East: Baron Cameron Avenue to Colvin Forest Drive:
  • Completed testing of the relocated segment of the Fairfax County Water Authority's 54" water main on the east side of Colvin Forest Drive along eastbound Route 7.  
  • Stage 2 construction pending right-of-way acquisition.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Activated the new Colvin Run stream channel.
  • Began excavation for the retaining wall between eastbound Route 7 and the Colvin Run stream channel.  
  • Completed the installation of the concrete footings, arch sections and wingwalls for the south half of the pedestrian underpass. 

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Placed cement-treated aggregate and base asphalt, followed by underdrain installation and curb stone placement along westbound Route 7 between Middleton Ridge Road and Trotting Horse Lane.
  • Began grading along westbound Route 7 between Trotting Horse Lane and Forestville Drive.
  • Completed the water main relocation between Beulah Road and Towlston Road.
  • Placed cement-treated aggregate and base asphalt along eastbound Route 7 between Old Ash Grove and Jarrett Valley Drive.

Click here to see April 2021 photos.

March 2021

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)

Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Continued noise barrier construction between Reston Avenue and Utterback Store Road.
  • Completed construction of the retaining wall along westbound Route 7 west of Utterback Store Road.
  • Storm sewer installation and earth-moving activities continued between Reston Avenue and Baron Cameron Avenue.
Area 1 East: Baron Cameron Avenue to Colvin Forest Drive:
  • Continued relocating approximately 1,100 feet of the Fairfax County Water Authority's 54-inch water main on the east side of Colvin Forest Drive along eastbound Route 7. 
  • Stage 2 construction pending right-of-way acquisition.

Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)

  • Completed construction of the east half of the box culvert under Carpers Farm Way.  
  • Completed the installation of the articulated block lining in the new Colvin Run channel and prepared for stream activation.
  • Continued excavation and began installing the concrete footers for the pedestrian underpass under Route 7. 
  • Began demolition of the southern half of the existing bridge over Difficult Run.

Area 4: Faulkner Drive to Jarrett Valley Drive

  • Water main relocation work between Beulah Road and Towlston Road was ongoing.

Click here to see March 2021 photos.

February 2021

Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Continued noise barrier construction between Reston Avenue and Utterback Store Road.
  • Began construction of the retaining wall west of Utterback Store Road along westbound Route 7.
  • Storm sewer installation and earth-moving activities continued between Reston Avenue and Baron Cameron Avenue.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way:
  • Started installation of the 54" water main relocation between Colvin Forest Drive and Carpers Farm Way.
  • Stage 2 construction pending right-of-way acquisition.
  • Continued the installation of the articulated block lining in the new Colvin Run channel.
  • Resumed excavation for the pedestrian underpass under Route 7. 
  • Commenced installation of the east half of the box culvert under Carpers Farm Way.
  • Finished placement of four elliptical storm sewer pipes at the east end of Colvin Run.
  • Water main relocation work between Beulah Road and Towlston Road was ongoing.
  • Removed the existing asphalt of the old eastbound Route 7 lanes between Lewinsville Road and Jarrett Valley Drive.
  • Reestablished direct access between eastbound Route 7 and Old Ash Grove.

Click here to see February 2021 photos.

January 2021

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Continued noise barrier construction between Reston Avenue and Utterback Store Road.
  • Storm sewer installation continued between Reston Avenue and Baron Cameron Avenue.
  • Completed the north extension of the Piney Run box culvert.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way:
  • Removed existing asphalt between Baron Cameron Avenue and Colvin Run Road (east end).
  • Shifted Carpers Farm Way traffic to the north in preparation for the installation of the new Colvin Run box culvert on the east side of Carpers Farm Way.
Area 2: Baron Cameron Intersection
  • Stage 2 construction pending right-of-way acquisition.
Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)
  • Commenced the installation of the articulated block lining in the new Colvin Run channel.
  • Continued earth-moving activities between Difficult Run and Faulkner Drive.
  • Began excavation for the pedestrian underpass under Route 7. 
Area 4: Faulkner Drive to Jarrett Valley Drive
  • Continued the water main relocation between Beulah Road and Towlston Road.
  • Shifted traffic on eastbound Route 7 to the north between Lewinsville Road and Jarrett Valley Drive.

Click here to see January 2021 photos.

December 2020

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Continued noise barrier construction between Reston Avenue and Utterback Store Road.
  • Storm sewer installation continued between Reston Avenue and Reston Parkway, and commenced between Utterback Store Road and Baron Cameron Avenue.
  • Placed cement-treated aggregate and base asphalt between Reston Parkway and Utterback Store Road. 
  • Reconstructed and reopened the intersection of Route 7 and Great Passage Boulevard.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Continued earth-moving operations between Baron Cameron Avenue and Carpers Farm Way.
  • Finished cement-treated aggregate and base asphalt placement and completed curb and gutter along eastbound Route 7 between Baron Cameron Avenue and Carpers Farm Way.
Area 2: Baron Cameron Intersection
  • Stage 2 construction pending right-of-way acquisition.
Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)
  • Continued earth-moving activities between Difficult Run and Faulkner Drive.
  • Continued construction of the new channel for Colvin Run Stream.
Area 4: Faulkner Drive to Jarrett Valley Drive
  • Continued storm sewer installation for Route 7 westbound lanes between Faulkner Drive and Trotting Horse Lane.  
  • Began relocating the water main between Beulah Road and Towlston Road.  
  • Completed asphalt placement and shifted traffic along westbound Route 7 between Lewinsville Road and Jarrett Valley Drive.
Click here to see December 2020 photos.

November 2020

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Continued noise barrier post installation and storm sewer work between Reston Avenue and Reston Parkway.
  • Earth-moving and grading activities between Reston Avenue and Utterback Store Road continued.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Continued earth-moving operations between Baron Cameron Avenue and Carpers Farm Way.
  • Finished cement-treated aggregate and base asphalt placement and completed curb and gutter along eastbound Route 7 between Baron Cameron Avenue and Carpers Farm Way.
Area 2: Baron Cameron Intersection
  • Stage 2 construction pending right-of-way acquisition.
Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)
  • Continued earth-moving activities between Carpers Farm Way and Colvin Forest Drive.
  • Started earth-moving activities between Difficult Run and Faulkner Drive.
  • Built temporary access road to the sewer pump station near Difficult Run.
  • Completed sheet pile installation in the Colvin Run area east of Carpers Farm Way.
Area 4: Faulkner Drive to Jarrett Valley Drive
  • Continued storm sewer installation for Route 7 westbound lanes between Faulkner Drive and Trotting Horse Lane.  
  • Placed cement-treated aggregate, installed underdrain, placed base asphalt and commenced curb and gutter installation along westbound Route 7 between Faulkner Drive and Trotting Horse Lane.  
  • Performed cement stabilization of the subgrade, placed cement-treated aggregate, installed underdrain, placed base asphalt and completed curb and gutter installation between Lewinsville Road and Jarrett Valley Drive.
Click here to see November 2020 photos.

October 2020

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Completed the extension of the Dog Run box culvert on the north side of Route 7 between Northfalls Court and Utterback Store Road.
  • Continued drilling noise barrier foundations and earth-moving activities between Reston Avenue and Utterback Store Road.
  • Began construction of noise barriers.
  • Performed storm sewer installation between Reston Avenue and Reston Parkway, and completed storm sewer installation between Reston Parkway and Utterback Store Road.
  • Performed cement stabilization of the subgrade and placed cement-treated aggregate for future westbound Route 7 lanes between Great Passage Boulevard and Amanda Drive.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Completed construction of the common duct bank between Delta Glen Court and Carpers Farm Way.
  • Continued earth-moving operations between Baron Cameron Avenue and Carpers Farm Way.
  • Completed storm sewer installation and performed fine grading and cement stabilization of the subgrade along eastbound Route 7 between Baron Cameron Avenue and Colvin Forest Drive.
Area 2: Baron Cameron Intersection
  • Stage 2 construction pending right-of-way acquisition.
Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)
  • Continued relocation of communication utilities.
  • Continued the realignment of Colvin Run.
  • Installed sheet pile in the Colvin Run area east of Carpers Farm Way.
  • Completed installation of the west half of the box culvert under Carper's Farm Way.
Area 4: Faulkner Drive to Jarrett Valley Drive
  • Continued storm sewer and completed water line installation for Route 7 westbound lanes between Faulkner Drive and Trotting Horse Lane.  
  • Began fine grading and cement stabilization of the subgrade for Route 7 westbound lanes between Faulkner Drive and Trotting Horse Lane.   
  • Completed storm sewer and water line installation for Route 7 westbound lanes between Lewinsville Road and Jarrett Valley Drive.
  • Continued construction of stormwater management pond near Trotting Horse Lane.
  • Continued earth-moving operations and completed fine grading for Route 7 westbound lanes between Lewinsville Road and Jarrett Valley Drive.

Click here to see October 2020 photos.

September 2020Drilled foundations for noise barrier

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Shifted traffic along Route 7 between Utterback Store Road and Baron Cameron Avenue.
  • Began construction of the extension of the Dog Run box culvert on the north side of Route 7 between Northfalls Court and Utterback Store Road.
  • Commenced drilling noise barrier foundations between Reston Avenue and Reston Parkway.
  • Continued tree clearing and earth-moving activities between Reston Avenue and Utterback Store Road.
  • Continued construction of stormwater management pond west of Baron Cameron Avenue.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Completed construction of the common duct bank between Baron Cameron Avenue and Delta Glen Court.
  • Started construction of the common duct bank between Delta Glen Court and Carpers Farm Way.
  • Continued earth-moving operations between Baron Cameron Avenue and Carpers Farm Way.
  • Continued storm sewer installation.
Area 2: Baron Cameron Intersection
  • Stage 2 construction pending right-of-way acquisition.
Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)
  • Continued relocation of communication utilities.
  • Continued the temporary realignment of Colvin Run.
  • Installed sheet pile in the Colvin Run area east of Carpers Farm Way.
  • Completed setting precast elements of the triple box culvert on the west side of Carpers Farm Way.
Area 4: Faulkner Drive to Jarrett Valley Drive
  • Began the installation of a water line between Middleton Ridge Road and Trotting Horse Lane.
  • Started storm sewer and water line installation between Lewinsville Road and Jarrett Valley Drive.
  • Continued construction of stormwater management pond near Trotting Horse Lane.
  • Continued earth-moving operations between Lewinsville Road and Jarrett Valley Drive.

Click here to see September 2020 photos.

August 2020

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
Area 1 West: Reston Avenue to Baron Cameron Avenue:
  • Completed reconstruction of the Bishopsgate Way and Markell Court intersections.  
  • Began clearing operations between Reston Avenue and Utterback Store Road.
  • Continued storm sewer installation.
  • Placed asphalt for future eastbound lanes and shifted westbound traffic to the south between Utterback Store Road and Baron Cameron Avenue.  
  • Continued construction of stormwater management pond west of Baron Cameron Avenue.
  • Continued clearing trees along westbound Route 7 between Reston Avenue and Utterback Store Road.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Began construction of the common duct bank between Baron Cameron Avenue and Delta Glen Court.
  • Started earth-moving operations between Baron Cameron Avenue and Carpers Farm Way.
  • Continued storm sewer installation.
Area 2: Baron Cameron Intersection
  • Stage 2 construction pending right-of-way acquisition.
Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)
  • Continued relocation of communication utilities.
  • Continued the temporary realignment of Colvin Run.
  • Installed sheet pile in the Colvin Run area east of Carpers Farm Way.
  • Continued construction of the triple box culvert and set precast concrete elements on the west side of the Carpers Farm Way.
Area 4: Faulkner Drive to Jarrett Valley Drive
  • Placed asphalt for temporary lanes in the median of Route 7 between Towlston Road and Lewinsville Road.  
  • Shifted Route 7 traffic to the south between Towlston Road and Lewinsville Road.
  • Continued construction of stormwater management pond near Trotting Horse Lane.
  • Began earth-moving operations between Lewinsville Road and Jarrett Valley Drive.

Click here to see August 2020 photos.

July 2020

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
Area 1 West: Reston Avenue to Baron Cameron Avenue
  • Continued storm sewer installation. 
  • Installed underdrain.
  • Placed curb stone and asphalt for future eastbound lanes.  
  • Continued construction of stormwater management pond west of Baron Cameron Avenue.
  • Shifted traffic on Route 7 between Reston Avenue and Utterback Store Road.  
  • Continued clearing trees along westbound Route 7 between Reston Avenue and Utterback Store Road.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Removed existing asphalt along eastbound Route 7 between Baron Cameron Avenue and Carpers Farm Way.  
  • Continued storm sewer installation.
Area 2: Baron Cameron Intersection
  • Stage 2 Construction pending right-of-way acquisition.
Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)
  • Continued relocation of communication utilities.
  • Began temporary realignment of Colvin Run.
  • Commenced excavation for and construction of the triple box culvert under Carpers Farm Way.
Area 4: Faulkner Drive to Jarrett Valley Drive
  • Placed asphalt for temporary lanes in the median of Route 7 between Atwood Road and Lewinsville Road.  
  • Shifted traffic on Route 7 between Atwood Drive and Towlston Road, and between Lewinsville Road and Jarrett Valley Drive.
  • Continued construction of stormwater management pond near Trotting Horse Lane.

Click here to see July 2020 photos.

June 2020

Area 1: Reston Avenue to Colvin Forest Drive (Except Baron Cameron Avenue Intersection)
Area 1 West: Reston Avenue to Riva Ridge Drive
  • Continued storm sewer installation.  
  • Relocated communication lines.  
  • Installed underdrain.
  • Continued construction of stormwater management pond west of Baron Cameron Avenue.
  • Performed cement stabilization of the subgrade, placed cement-treated aggregate, and placed base asphalt for future eastbound lanes.
  • Prepared for shifting EB and WB traffic to the south in July.
Area 1 East: Baron Cameron Avenue to Carpers Farm Way
  • Completed cement stabilization of the subgrade, placed cement-treated aggregate, and placed base asphalt for temporary pavement in the median.
  • Shifted the eastbound Route 7 lanes towards the median.
  • Began reconstruction of the Delta Glen Court pavement across the future eastbound Route 7 lanes.
  • Built a retaining wall west of Baron Cameron Avenue.
Area 2: Baron Cameron Intersection
  • Stage 2 Construction pending right-of-way acquisition.
Area 3: Difficult Run Area (Carpers Farm Way to Faulkner Drive)
  • Difficult Run/Colvin Run area: Continued relocation of communication utilities.
  • Prepared for start of temporary Colvin Run realignment in July.
  • Prepared for start of Carper's Farm Way triple box culvert installation in July.
Area 4: Faulkner Drive to Jarrett Valley Drive
  • Continued construction of stormwater management pond near Trotting Horse Lane.
  • Placed asphalt for temporary pavement in the median. 
  • Completed temporary shoulder strengthening along the eastbound lanes. 
  • Prepared for shifting EB and WB traffic to the south between Atwood Road and Lewinsville Road in July.

Click here to see June 2020 photos.

May 2020Looking East Along Route 7 from Reston Parkway

  • Difficult Run/Colvin Run area: Continued relocation of communication utilities.
  • Storm sewer installation between Utterback Store Road and Baron Cameron Avenue continued.
  • Relocated communications lines between Reston Parkway and Markell Court.
  • Began clearing and earth-moving for a stormwater management pond along westbound Route 7 near Trotting Horse Lane.
  • Continued earth-moving and grading between Reston Avenue and Reston Parkway.
  • Performed cement stabilization of the subgrade, placed concrete-treated aggregate, installed underdrain, and placed based asphalt for future eastbound lanes between Reston Parkway and Bishopsgate Way, and between Baron Cameron Avenue and Delta Glen Court.
  • Placed temporary asphalt in the Route 7 median between Faulkner Drive and Towlston Road in preparation for lane shifts.
  • Strengthened shoulders along westbound Route 7 between Faulkner Drive and Towlston Road.
  • Started earth-moving operations between McLean Bible Church and Jarrett Valley Drive.
  • Click here to see photos.

April 2020Shoulder Widening

  • Difficult Run/Colvin Run area
    • Utility installation work
    • Paving and striping for the lane shift between Carpers Farm Way/Colvin Run Road and Serenity Woods Lane/Faulkner Drive
  • Installed storm sewer between Reston Avenue and Reston Parkway, and between Utterback Store Road and Carpers Farm Way.
  • Cleared and graded for a stormwater management pond west of Baron Cameron Avenue.
  • Relocated communications lines between Reston Parkway and Utterback Store Road.
  • Continued earth-moving operations between Reston Avenue and Riva Ridge Drive.
  • Performed fine grading for permanent pavement between Reston Parkway and Utterback Store Road.
  • Placed cement stabilization materials and concrete-treated aggregate, and installed underdrain between Baron Cameron Avenue and Carpers Farm Way.
  • Grading and stone placement for temporary pavement in the median between Faulkner Drive and Towlston Road
  • Strengthened shoulders and placed asphalt between Faulkner Drive and Towlston Road.
  • Click here to see photos.

March 2020Jack and Bore for Storm Sewer

  • Difficult Run/Colvin Run area
    • Preparatory work for utility installation
    • Median grading for temporary paving between Carpers Farm Way and Serenity Woods Lane.
  • Installed storm sewer between Reston Avenue and Carpers Farm Way.
  • Relocated and tied-in a water line between Reston Avenue and Reston Parkway.
  • A third-party communications utility was relocated between Reston Avenue and Reston Parkway.
  • Continued earth-moving operations between Reston Avenue and Carpers Farm Way.
  • Graded for temporary paving in the median between Serenity Woods Lane and Beulah Road.
  • Removed topsoil for temporary paving in the median between Beulah Road and Towlston Road.
  • Click here to see photos.

February 2020Reston Parkway

  • Difficult Run/Colvin Run area--clearing, erosion & sediment (E&S) controls, utility installation and bridge median removal continued.
  • Cleared and installed E&S controls along eastbound Route 7 from Baron Cameron Avenue to Carpers Farm Way.
  • Removed topsoil between Reston Parkway and Utterback Store Road. 
  • Continued earth-moving operations between Reston Avenue and Bishopsgate Way.
  • Installed storm sewer between Reston Avenue and Delta Glen Drive.
  • Relocated water main between Reston Avenue and Reston Parkway. 
  • Placed barrier along the median of Route 7 between Lewinsville Road and Jarrett Valley Drive.
  • Click here to see photos.

January 2020

  • Difficult Run/Colvin Run area:
    • Began preparatory work within the VDOT right of way for utility relocations.
  • Placed roadway fill between Reston Avenue and Utterback Store Road.
  • Continued earth-moving operations between Utterback Store Road and Bishopsgate Way.
  • Removed topsoil between Baron Cameron Avenue and Faulkner Drive.
  • Installed storm sewer between Reston Avenue and Baron Cameron Avenue, including tunneling under Route 7 just west of Bishopsgate Way.
  • Completed of shoulder-strengthening along eastbound Route 7 between Lewinsville Road and Jarrett Valley Drive.
  • Click here to see photos.

December 2019Median Demo

  • Completed pavement demolition between Reston Parkway and Baron Cameron Avenue
  • Placed roadway fill between Reston Avenue and Utterback Store Road
  • Conducted earth-moving operations between Utterback Store Road and Bishopsgate Way
  • Cleared tree and brush and installed erosion and sediment controls within the VDOT right-of-way between Reston Avenue and Bishopsgate Way
  • Installed storm sewer between Reston Avenue and Markell Court
  • Placed traffic barrier along the Route 7 median between Baron Cameron Avenue and Delta Glen Court
  • Difficult Run/Colvin Run area:
    • Removed the raised median at the Difficult Run bridge
  • Removed topsoil between Baron Cameron Avenue and Delta Glen Drive
  • Strengthened the right shoulder of eastbound Route 7 between Lewinsville Road and Jarrett Valley Drive.
  • Click here to see photos.

November 2019

  • Continued storm sewer installation between Reston Parkway and Reston Avenue.
  • Demolished former eastbound Route 7 pavement from Reston Avenue to Bishopsgate Way.
  • Placed roadway fill between Reston Avenue and Utterback Store Road.
  • Installed erosion and sediment controls prior to clearing between Reston Avenue and Utterback Store Road.
  • Placed barrier and constructed asphalt wedge for drainage along westbound Route 7 between Colvin Run Road/Carpers Farm Way and Baron Cameron Avenue.
  • Cut and capped an unused water line stub along the McLean Bible Church access road.
  • Click here to see photos.

October 2019

  • Opened early improvements at Towlston Road (original target date was Summer 2020).
  • Completed Stage 1B storm sewer installation between Amanda Drive and Baron Cameron Avenue.
  • Crews finished construction of the temporary eastbound Route 7 lanes in the median between Reston Parkway and Baron Cameron Avenue.  
  • Completed weekend intersection reconstruction activities at Reston Parkway, Utterback Store Road, and Markell Court/Amanda Drive.
  • Shifted eastbound Route 7 traffic to the median between Reston Avenue and Baron Cameron Avenue.
  • Completed shoulder strengthening on westbound Route 7 between Faulkner Drive and Baron Cameron Avenue and implemented a minor lane shift to the north.
  • Click here to see photos.

September 2019

Aerial View Looking West

  • Storm sewer installation between Amanda Drive and Baron Cameron Avenue continued.
  • Continued work in the median to construct temporary eastbound lanes between Reston Avenue and Amanda Drive/Markell Court.
    • Completed fine grading and soil cement operations.
    • Completed placement of cement-treated aggregate.
    • Graded and placed stone for temporary asphalt.
    • Placed base and intermediate asphalt.
  • Crews performed test-pitting for utilities on Towlston Road in preparation for temporary improvements at the Route 7/Towlston Road intersection.
  • Click here to see photos.

August 2019

CTA

  • Completed early improvements at Baron Cameron Avenue; opened third left-turn lane from westbound Route 7 to Baron Cameron Avenue 10 days prior to contract date. Click here to see a Twitter video.
  • Work on early improvements between Reston Avenue and Baron Cameron Avenue began in mid-August:
    • Placed fill materials for the temporary and permanent widening in the median.
    • Began soil cement stabilization operations in the median of Route 7 to provide a base for future pavement sections.
    • Installed sub-base Cement Treated Aggregate (CTA) in areas of soil cement stabilization in the median.
    • Placed temporary pavement 21-B aggregate in median.
    • Continued the installation and monitoring of erosion & sediment (E&S) control measures for all disturbed areas.
    • Continued drainage work in the median of Route 7.
    • Placed asphalt in the median of Route 7 for temporary and permanent widening.
  • Based on feedback from the community, additional enhancements along the corridor during August included:
    • Placement of rumble strips on Utterback Store Road to warn drivers of the Forestville Elementary School Zone.
    • Installation of pavement markings and “Do Not Block Intersection” signage on Towlston Road at Vernon Drive.
    • Construction of temporary turn taper on westbound Route 7 to facilitate deceleration and turning at Northfalls Court.
  • Click here to see photos.

July 2019

  • Utility relocation work continued near the Route 7/Baron Cameron Avenue intersection.
  • Completed shoulder widening on north side of westbound Route 7 west of Baron Cameron Avenue.
  • Installed temporary signals to accommodate upcoming traffic shifts at Reston Parkway, Utterback Store Road, and Baron Cameron Avenue.
  • Traffic was shifted slightly to the north on westbound Route 7 between Reston Avenue and Baron Cameron Avenue.
  • Began installation of barrier to protect the median work area west of Amanda Drive.
  • Continued earth moving operations west of Utterback Store Road.
  • Began storm sewer installation between Reston Avenue and Reston Parkway.
  • Click here to see photos.

June 2019

  • Started utility relocations near the Route 7/Baron Cameron Avenue intersection.
  • Completed grading and placement of stone for shoulder widening west of Utterback Store Road.
  • Installed concrete traffic barrier in the median west of Reston Parkway.
  • Removed topsoil from the median west of Utterback Store Road.
  • Began earth moving activities in the median west of Reston Parkway.
  • Began installing storm pipe and structures on the east side of the Reston Avenue intersection.
  • Relocated the pedestrian poles for the Utterback Store Road intersection.
  • Click here to see photos.